Case Studies
Remediation, Groundworks, External Works and Concrete Frame, RAF Brize Norton
Groundworks
CLIENT: Interserve
CONTRACT VALUE: £1,200,000
CONTRACT DURATION: 10 Months
A multi-disciplined project that brought together many of our core skills within the business. The project encompassed initial site remediation, the construction of all groundworks, foundation, external works and concrete frame for the construction of two new aircraft hangers and associated buildings and car parks.
The project duration was 10 months, which involved working in close partnership with MOD personnel and the principle contractors on a very busy military establishment where security was paramount.
Back to top