4 storey frame, APU
Concrete Frames & Structures
CLIENT: William Verry Ltd
CONTRACT VALUE: £2,000,000
CONTRACT DURATION: 30 Weeks
The construction of a 4 storey college block and associated infrastructure works.
This was a challenging project compounded by a large amount of downstand beams and a curved structure, however we succeeded on getting this contract completed within the programme.
The project was constructed using an Ischebeck Titan Table System for the slabs and walls were formed using the Peri Trio System.
Floor areas of 800m2 were completed on a 3 week cycle time.